Durations come from quantities; the critical path is worked out for you.
Tasks are generated from the BOQ. Each duration is the work content divided by the crew size, so changing quantities changes the programme.
Link tasks with finish-to-start or other dependencies. The critical path (tasks with no float) is highlighted — a delay to any of them delays completion.
Add public holidays and shutdowns in calendar settings; every view and export uses the same calendar.